 (2) GPP BIG FIELD LLP V  SOLAR EPC SOLUTIONS SL 

 (2) GPP BIG FIELD LLP V  SOLAR EPC SOLUTIONS SL 

by Nahema ALLAILI | May 31, 2024 | Liquidated Damages, Penalty, Terms of Contract

RELEVANT CONTRACT PROVISIONS Clause 3.1. The Contractor hereby accepts the commitment to carry out the Works, in the time specified in the Agreement and the timetable attached hereto as Annexure 3, at his own risk, delivering the PV Project fully completed, started-up...
 (1) GPP BIG FIELD LLP V  SOLAR EPC SOLUTIONS SL 

 (1) GPP BIG FIELD LLP V  SOLAR EPC SOLUTIONS SL 

by Nahema ALLAILI | Apr 29, 2024 | Force majeure, Guarantee, Liquidated Damages, Penalty, Representation, Terms of Contract

RELEVANT CONTRACT PROVISIONS Clause 3.1. The Contractor hereby accepts the commitment to carry out the Works, in the time specified in the Agreement and the timetable attached hereto as Annexure 3, at his own risk, delivering the PV Project fully completed, started-up...
RTS Flexible Systems Ltd v Molkerei Alois Muller GmbH & Co KG [2010] 

RTS Flexible Systems Ltd v Molkerei Alois Muller GmbH & Co KG [2010] 

by Nahema ALLAILI | Aug 14, 2023 | Terms of Contract, Uncategorized, Uncategorized

Intention to create legal relations. Agreement subject to contract. Letter of intent setting out draft contract with standard terms to take effect when executed   Letter of intent expiring with negotiations as to detailed terms continuing and work having commenced...
Smith v Hughes (1870–1871) 

Smith v Hughes (1870–1871) 

by Nahema ALLAILI | Aug 7, 2023 | Contract law, Terms of Contract, Uncategorized, Uncategorized

Smith V Hughes is a landmark case in English contract law that dealt with the issue of contract formation and the interpretation of contractual terms. Facts of the Case: The case involved a dispute between Mr. Smith, the plaintiff, and Mr. Hughes, the defendant. Mr....
BRITISH OVERSEAS BANK NOMINEES LTD V STEWART MILNE GROUP LTD

BRITISH OVERSEAS BANK NOMINEES LTD V STEWART MILNE GROUP LTD

by Nahema ALLAILI | Sep 10, 2019 | Collateral Warranty, Contract law, Law of prescription, Terms of Contract

RELEVANT CONTRACT PROVISIONS DB / Scot. Cl. 2.1.1 (Basic obligation) The Contractor shall carry out and complete the Works in a proper and workmanlike manner and in compliance with the Contract Documents, the Construction Phase Plan, and the Statutory Requirements and...